30-set-22 1 Kick Off Meeting WP1 1-DCU Achieved
31-ott-22 2 Consortium Agreement WP1 1-DCU Achieved
31-ago-23 12 Planned recruitments completed WP2, WP3, WP4, WP5 1-DCU Achieved
31-ago-23 12 All recruited fellows enrolled in PhD programme WP2, WP3, WP4, WP5 1-DCU Achieved
30-nov-23 15 Project mid-term check at month 13-15 WP2, WP3, WP4, WP5 1-DCU Achieved
29-feb-24 18 Summer School 1 WP6 2-UiS Achieved
31-ago-25 36 Data collection completed WP2 WP2 WP2 5-IPA
31-ago-25 36 Data collection completed WP3 WP3 WP3 1-DCU
31-ago-25 36 Data collection completed WP4 WP4 WP4 1-DCU
31-ago-25 36 Data collection completed WP5 WP5 WP5 2-UiS
31-ago-25 36 Summer School 2 WP6 1-DCU
30-giu-26 46 Final conference WP7 1-DCU
31-ago-26 48 10 PhD Theses WP2, WP3, WP4, WP5 1-DCU
31-ago-26 48 Final report WP1 1-DCU